Melton - LXRP
Our engineering team integrated within the Northwestern Program Alliance development team, where we managed +$150 million of scope in the TOC phase of Melton Level Crossing removal project for NWPA.
We led the civil, earthworks, drainage, retaining walls, roads, carparks and Lanscaping from Design development to staging, methodology, program and procurement.
Melton will be boom gate free in 2026 by removing 4 dangerous and congested level crossings at:
About 73,000 vehicles travel through these crossings each day, with the boom gates down for up to 28 minutes of the morning peak.
Retaining Walls (L-Walls)
Drainage & Overland Flow
Cut to Subgrade
Material Reuse
Earthworks
Track Drainage
Civil Profiles
Material Reuse
Formation Construction & Tie in
Roadworks
Hardstand Construction
Management of Contaminants
Design Development
Methodology Development & Planning
Discipline Interface and Collaborative Planning
Procurement Strategy
Subcontractor Engagement & Collaboration
Programming & Occupation Programming
Engineering Resource Management